Ore Raymond mill installation and commissioning.

If you are interested in our products, Please get in contact with us .

E-mail: shuguang_mill@163.com Chat Line Send Inquiry

The ore Raymond mill is a commonly used powder equipment, the equipment accessories are many, there are crusher, feeder, fan, motor, transmission pipeline, host, dust collector and dust collector. The installation and debugging should pay attention to five problems to ensure that the installation can run properly.

 

1. The installation position of ore Raymond mill and crusher has a lot to do, the different broken ground, ore Raymond mill installation location is different also, most commonly installed in the workshop or outdoor job.

 

2. Before the installation of the ore Raymond mill, check the packing list according to the packing list to check whether there is any damage, spare parts and spare parts in the transportation process.

 

3. Check the connection of all parts, should be firm and reliable, carefully check whether there is any foreign body on the impeller, if any, should be eliminated in time. Check whether the motor wiring is correct and the voltage is normal.

 

4. The adjustment of the machine crusher, before they go out factory factory running for hours and ministries are normal, even so, the ore after Raymond mill site installation in place, still should conduct a comprehensive inspection to check whether the oil pipe connection, should be to add a oil before test run, to join "mobil automobile lubricant".

 

5. Before installing the belt, start the motor, sign XuanXiangYing and sand making machine in the same direction from the feeding mouth, namely if impeller counterclockwise rotation with the sign in the opposite direction, should adjust motor wiring, make its spin to agree and sign direction for double motor drive on both sides of the spindle assembly and motor respectively connected to the spindle assembly with the same number of triangle tape on both sides of the triangle belt tensioning force the same should be adjusted and flat.

 

Send Inquiry

We guarantee that your information will not be divulged to third parties and reply to you within 24 hours.

Please enter your demand such as Raw material type, Capacity, Feeding material size, Final product size, etc. To become our quality clients will have access to a discount of contract!

  • Product Name
  • Your Name
  • Your Email
  • Your Phone
  • Requirements

Hot Products